ExxonMobil has made two new discoveries offshore Guyana at Seabob and Kiru-Kiru. These are the sixth and seventh in Guyana this year, with the total number of discoveries in Guyana at more than 25.
The Seabob and Kiru-Kiru discoveries will add to the previous discovered recoverable resource estimate for the Stabroek Block of approximately 11 billion barrels of oil equivalent.
Liza Unity and Liza Destiny FPSOs have reached their combined design capacity of more than 360,000 gross barrels of oil per day.
The Seabob-1 well encountered approximately 131 feet (40 meters) of high-quality hydrocarbon-bearing sandstone and was drilled in 4,660 feet (1,421 meters) of water by the Stena Carron drill ship. The Kiru-Kiru-1 well encountered approximately 98 feet (30 meters) of high-quality hydrocarbon-bearing sandstone and was drilled by the Stena DrillMAX in 5,760 feet (1,756 meters) of water. Drilling operations at Kiru-Kiru are ongoing.
“ExxonMobil and its partners continue to accelerate exploration, development and production activities for the benefit of all stakeholders, including the people of Guyana,” said Liam Mallon, president of ExxonMobil Upstream Company. “The resources we are investing in and discovering offshore Guyana will provide safe, secure energy for global markets for decades to come.”
The company’s 2022 investment plans include further exploration drilling and resource development in Guyana, where it is already increasing production at an accelerated, industry-leading pace. Two floating production storage and offloading (FPSO) vessels operating offshore Guyana — Liza Destiny and Liza Unity — have exceeded their initial combined production target of 340,000 barrels of oil per day.
The Liza Phase 1 development, which began production in December 2019, reached its new production capacity of more than 140,000 gross barrels of oil per day in the second quarter of 2022 following production optimization work on the Liza Destiny floating production, storage, and offloading vessel (FPSO).
The Liza Phase 2 development, which achieved first oil in February 2022 utilizing the Liza Unity FPSO, reached its production capacity of approximately 220,000 gross barrels of oil per day earlier this month.
A third project, Payara, is expected to produce 220,000 barrels per day. Construction on its production vessel, the Prosperity FPSO, is approximately five months ahead of schedule with start-up likely before year-end 2023.
The fourth project, Yellowtail, is expected to produce 250,000 barrels per day when the ONE GUYANA FPSO comes online in 2025.
At least six FPSOs with a production capacity of more than 1 million gross barrels of oil per day are expected to be online on the Stabroek Block in 2027, with the potential for up to 10 FPSOs to develop gross discovered recoverable resources.
Guyana’s Stabroek block is 6.6 million acres (26,800 square kilometers). ExxonMobil affiliate Esso Exploration and Production Guyana Limited is the operator and holds 45% interest in the block. Hess Guyana Exploration Ltd. holds 30% interest, and CNOOC Petroleum Guyana Limited holds 25% interest.